Tuesday, 21 November 2023 09:23

Norochcholai Coal power plant break down persists for 14 days Featured

The Ceylon Electricity Board (CEB) yesterday (19) stated that it would take a minimum of 14 days to repair the Unit 2 generator of the Lakvijaya Power Plant in Norochcholai, which broke down, resulting in the loss of 300 Megawatt (MW) of generation capacity to feed the national grid.

According to the statement issued by the CEB last week, the high-pressure heater system of the generating unit had malfunctioned. The CEB said the power plant’s employees had already initiated preliminary measures to restore the out-of-order generating unit

The Norochcholai coal power plant – built by a Chinese State-owned firm – has been in the spotlight for numerous controversies, including multiple breakdowns and several all-island power outages.

CEB Chairman Nalinda Ilangakoon said that it would have no impact on national electricity generation since hydropower electricity production had gone up as a result of ongoing heavy showers.

 

 

World News

Latest World News

There are 35832 listings and 1274 categories in our website