The China-Pakistan Engro Consortium was selected last year as part of a step towards reducing the cost of power production.
However, last Monday, Power and Energy Minister Kanchana Wijesekera submitted a Cabinet paper titled “Revisiting the National Energy Policy Related to the Development of Natural Gas Infrastructure in the Country,” to suspend the ongoing LNG procurement process.
Accordingly, the suspension covers the Development of a Floating Storage and Re-gasification Unit (FSRU) off Kerawalapitiya on a Build, Own, and Operate basis and a compatible mooring system on Build, Own, Operate and Transfer basis.
It also covers the associated projects – the development of Offshore and Onshore Re-gasification Liquefied Natural Gas (RLNG) Transmission Pipeline Network with an Onshore Receiving Facility (ORF).
It is associated with System from the Floating Storage and Re-gasification Unit (FSRU) to existing and future Kerawalapitiya and Kelanitissa Power Plants on Build, Own, Operate and Transfer (BOOT) basis.